Rethinking Planning and Estimation in Hardware Development

Hardware Development Team Meeting

Scrum has been widely adopted in software development, but applying it to hardware engineering raises questions about which Scrum practices translate successfully and which require adaptation. This article draws on a Scrum transformation I led for a team at a biotechnology company developing a new mass spectrometer.

The engagement provided an opportunity to test a conclusion I had reached during eighteen months of prior research: while the Scrum framework itself translates well to hardware development, many software-oriented implementation practices do not.

The differences between hardware and software development are not merely procedural, but structural. Some of those differences concerned planning, estimating, and forecasting, where long lead times and specialized engineering skills required several important adaptations.

Release Planning Around Long Lead Times and Dependencies

Release planning is not a Scrum practice, but it is commonly used when multiple Scrum teams need to coordinate their work. A release plan maps out work to be done over some collection of Sprints, which means that it is a medium- to long-range plan of work to be done over time.

In the world of software development, release planning tends to be necessary when more than two or three Scrum teams have to collaborate and synchronize their work in order to develop their product successfully. If Team B, for example, depends on Team A completing a particular deliverable in Sprint 3 so they can build something in Sprint 4, then Team A needs to know this before Sprint 3 starts.

Thus, a key driver behind the need for release planning in software development is the need to identify cross-team dependencies in advance, so that the dependencies can be managed successfully. Otherwise, many dependencies may be broken, causing delays and schedule churn.

The cross-team dependency-management problem largely disappears when the product is developed by a single Scrum team.

The cross-team dependency-management problem largely disappears when the product is developed by a single Scrum team. In that case, the team members can simply sequence their work to satisfy their own needs without having to coordinate dependencies with other Scrum teams. Indeed, many Scrum teams that individually build a software product dispense with longer-term planning entirely, instead planning one Sprint at a time.

Why hardware teams need longer-range planning

The need to avoid breaking dependencies in a multi-team hardware-development project reflects the same driver for release planning as in the software world. However, unlike the software case, hardware teams typically need release planning even when there are no external dependencies on other teams. The reason is that hardware development is constrained not only by the work of other teams, but also by the physical realities of developing and building the product.

Hardware engineering involves long lead-time constraints, such as around component procurement, printed-circuit board fabrication, prototype builds, access to shared test facilities, and so on. The problem becomes more acute when there is a dependency on external suppliers to provide components and services, especially when the orders have to be scheduled months in advance.

Risk management is another area that is different for hardware engineering compared to software engineering. Product development often depends on parts from external suppliers, internal needs that are identified but may or may not be possible to satisfy, and integration risks. These risks must be identified and mitigated as early as possible in the schedule, a process that may span multiple Sprints. Here again we see the need for long-term planning.

The team’s three development milestones

This team found the need for release planning to be a natural one, as they were used to thinking in terms of multi-month milestones. After some discussion, they settled on an overall plan of three release cycles, each tied to a major development milestone.

The first release cycle would produce a functional prototype that proved the product concept. The second release cycle would produce a manufacturing prototype, representing the first attempt at a manufacturable design. Experience had shown, however, that this design would still require further development before it was ready for production. The third Release cycle would produce the final manufacturable design.

Crucially, and unlike the usual software model, these release cycles did not follow a cadence model.

Crucially, and unlike the usual software model, these release cycles did not follow a cadence model. Rather, they were oriented around the fixed scope of what had to be accomplished to achieve each milestone.

The purpose of release planning in hardware development is not primarily to predict delivery dates. It is to expose dependencies, constraints, and risks while there is still enough time to address them. For that reason, release planning becomes essential even when the product is being developed by a single Scrum team.

Why This Team Chose Person-Days Over Story Points

Scrum trainers commonly advocate story points as preferred units for estimating the size of stories to be planned into Sprints or release cycles. These units reflect relative sizing of stories with respect to each other, often using numbers from the Fibonacci sequence, and are not tied to time or anything else measurable.

Establishing the story-point reference scale for a new Scrum team requires that the team members have an existing set of stories, ranging from small to large, which they sort in order of an intuitive sense of size, and to which they then assign Fibonacci numbers. To do this, the team members must all understand the reference stories the same way; i.e., they must have a shared norm for what “size” means.

In cross-functional hardware teams, the specialized nature of the work can make it difficult to establish a shared sense of size across specialties. A mechanical engineer may have little basis for deciding whether a particular FPGA design task is twice as large as another FPGA design task, just as an electrical engineer may have difficulty comparing two mechanical-design tasks. Thus, the team could not establish a shared reference scale for story points.

What can be done is to use effort-based units expressed in terms of effort, rather than units representing calendar duration.

What can be done is to use effort-based units expressed in terms of effort, rather than units representing calendar duration. In this model, the units are Person-Days, where one Person-Day is eight hours of time spent working on a Story. Note that a Story of size one Person-Day may take two calendar days to complete, as there are meetings and other distractions from development time that occur on most days.

Unlike story points, Person-Days do not require team members to establish a common relative-sizing scale across specialties.

The reaction of the team members to my explanations of story points and Person-Days was interesting. They wanted nothing to do with story points, and found Person-Days intuitive and easy to use.

The above perspective has been consistent across the hardware-development organizations with which I have worked. Hardware engineers have strongly preferred Person-Days to story points. In my experience, none have viewed story points as a natural or useful way to estimate work.

Forecasting How Much Work the Team Can Complete

Velocity is the amount of estimated work that a Scrum team completes in a Sprint. While we can look up the velocity for past Sprints, we require a forecast of velocity to plan the next Sprint. The forecasted velocity provides a ceiling for how much work the team can be expected to do in the Sprint. In the simplest model, the Scrum team estimates a ranked (sequenced) series of stories, and then fills the Sprint Backlog with the most valuable subset of the estimated stories that fits within the velocity ceiling.

The process of velocity forecasting for the team was about the only thing not affected by the difference between hardware and software development.

Velocity forecasting can use different methods depending on whether the units of estimation are story points or Person-Days. Four methods are described below.

If the units are story points, we can use “yesterday’s weather” and estimate the next Sprint’s velocity to be the same as what the last Sprint’s velocity was. Alternatively, we can take a running average of the last three Sprints’ velocity values as the forecast.

If the units are Person-Days, two additional methods become available. One method is to use the “focus factor” formula:

Velocity = (focus factor) x (# Team members)
x (# working days in the Sprint).

(A two-week Sprint, for example, would contain ten working days.) This is useful for a quick, rough estimate, in which case I use a focus factor of 0.6.

The resource model this team used

The other is a more refined “resource model” estimate, which does a per-person forecast of available working time, after subtracting off Scrum meetings, time off, and other known activities to try to come up with the available working time, and then sums these times across all team members. This is my preferred model for Sprint planning.

We used the resource-model approach for this team. The Scrum Master found it intuitive because the organization already had a concept of the aggregate engineering effort required to develop its products. Expressing that effort in Person-Days provided a straightforward way to translate that existing concept into a Sprint-level capacity forecast. He quickly estimated the team’s velocity using the spreadsheet template I gave him.

Unlike estimation units, the process of forecasting velocity for this team did not differ significantly from practices commonly used in software development.

Sprint Planning Around Specialized Skills and Availability

Unfortunately, knowing the velocity available to the team was only part of the planning problem for the team. The simple Sprint planning model described in the preceding section did not take into account the skills of the team members, and would have overloaded some members while leaving others underutilized. Velocity established the total amount of work that could be attempted during the Sprint, but specialization determined which work could realistically be assigned to each team member.

Prior to the Sprint planning meeting, the Scrum Master forecasted how much of each individual’s time would be available for work in the Sprint, and recorded that availability along with the individual’s specialty. This forecasting by specialty is not something that is typically done for software teams.

The initial step of the first part of the Sprint planning meeting would have been recognizable to a software team. The Product Owner and team members had previously written the stories to be estimated in the meeting. In the meeting, the Scrum Master facilitated the Planning Poker exercise, while the team members estimated the size of each story in Person-Days.

Then the team went through the top-ranked stories, identified which team members had the skills needed to do each one, and allocated the stories against each person’s available capacity so that no one was over- or under-allocated.

Then the team went through the top-ranked stories, identified which team members had the skills needed to do each one, and allocated the stories against each person’s available capacity so that no one was over- or under-allocated. The process was straightforward, but it was different from the standard Sprint planning model used by software teams.

In the second part of the Sprint planning meeting, the team members developed task breakdowns for each story planned into the Sprint. This exercise was followed by a final sanity check using the task estimates to ensure that the resulting set of stories represented a workload the team could realistically manage.

The lesson was that Sprint planning for hardware teams requires balancing not only total team capacity, but also the specialized skills and individual availability needed to complete each story.

This article summarizes several of the key observations from a larger Scrum implementation in a hardware development organization. A more detailed case study describing the implementation, the organizational context, and additional lessons learned is available here.

We hope you found this post informative

Before you move on, please consider supporting our non-profit mission by joining Agile Alliance today. This is a community blog post. The opinions contained within belong solely to the author or authors and may not represent the opinion or policy of Agile Alliance.

Picture of Kevin Thompson

Kevin Thompson

Kevin Thompson, Ph.D., is an Agile consultant, trainer, and author specializing in Agile hardware development. He has helped more than 100 engineering organizations worldwide modernize product development by adapting Scrum to the realities of hardware and embedded systems. He is the author of Solutions for Agile Governance in the Enterprise and writes about applying Agile principles to complex engineering environments.

Recent Blog Posts

Recent Posts

Join Agile Alliance!

$5 per month (paid annually)*

*Corporate plans are also available

Post your comments or questions

Recent Agile Alliance Blog Posts

Ready to join Agile Alliance?

Unlock members-only access to online learning sessions, Agile resources, annual conference discounts, and more! And when you join, you’ll be supporting our member initiatives, regional events, and global community groups.

IMPORTANT: We have transitioned to a new membership platform. If you have not already done so, you will need to SET UP AN ACCOUNT on the new platform to establish your user profile. Your previous login credentials will not work until you do this set up.

When you see the login screen, choose “Set up Account” and follow the prompts to create your new account. You can choose to log in using your social credentials for either Google or Linkedin (recommended), or you can set up your account using an email address.